This presentation aims to introduce the structure of ESA kit and demonstrate how to physically install it.
Compatible with Cubby V2 computing sled, this kit makes it easy to transform a 19 inch EIA rack to an OCP rack. We take the 8OU 19' standard ESA Kit as an example. Usually, there is a 16OU rack in the data center. In that case, the switch and the power shelf should be placed on the top of the servers instead of at the bottom.
The official ESA Kit installation document can be download in here. Note: this document is only accesible for MITAC user.
The official EdgeCore switch installation document can be download in here. Note: this document is only accesible for EdgeCore user.
Installation video in 5 mins: real example For the DC in Douai.